City of Ashland Paving Project

 

 

paving project

Updates on the Paving Project

In November 2016, the citizens of Ashland voted on and passed an income tax increase of .25 percent to generate additional funding to repave streets in the city. Updates regarding that project will be posted here as they become available.

Please note that the plans are contingent upon the weather and other factors. The contractor for the project is committed to doing a great job for the city and will make every effort to complete the job as efficiently as possible. 

To find out more about how weather conditions affect asphalt, check out this info from the Federal Highway Administration::
Federal Highway Administration Guidelines

Thank you for your patience as the crews work on the paving. The inconveniences will soon result in a more pleasant ride around the city for all of us!

 

 


 

What's Happening

Second Phase:

Arch St
Baney Rd
Broad St
Elmarna Ave
Franklin Ave
Myers Ave
Monroe St
Scott St

(added 7/20/17)

July 20, 2017 - The paving project will resume with Phase 2 during the first week of August. The streets scheduled for resurfacing are listed. 

Thank you for your assistance in observing the "No Parking" signs that are being posted before the work starts. 

 

 Morgan Avenue 

 

The paving of Morgan Avenue and other area streets during the summer of 2017.

 

 

Past Updates

First Phase:

Morgan Avenue
Budd Avenue
Avalon Drive
King Ridge Drive
Luray Drive
Eastern Ave (added 6/27)

July 14, 2017 - With the improved weather today, the crews plan to finish Eastern Ave and Luray Drive today.

July 11, 2017 - Eastern Ave is scheduled for paving today and then the crews will start on Luray, as there is little chance of rain. 

July 7, 2017 - Work will commence on Eastern Ave today, weather permitting.

July 6, 2017 - Avalon is almost finished while the paving continues on King Ridge Drive. Eastern Ave is scheduled for tomorrow, weather permitting. 

July 5, 2017 - Paving resumes today on King Ridge Drive and Avalon. 

Thank you for your assistance in observing the "No Parking" signs that are being posted before the work starts. 

June 30, 2017 - Sarver Paving is performing only cleanup work today and will resume paving next Wednesday when they will finish King Ridge Drive and potentially start on Avalon.  

June 29, 2017 - Budd Avenue and King Ridge Avenue are being paved today, weather permitting.

June 28, 2017 - Morgan Avenue is being paved today. Check back for updated information which will be posted as it is received. 

June 27, 2017 - Eastern Ave, starting at East Main and to Hillcrest has been added to the list for the first phase of the street paving. 

June 21, 2017Sarver will begin posting streets for "no parking" Wednesday (6/21/17), then milling (or pavement planing) is to start Friday (6/23/17) around 10:00am on Morgan Avenue. The current schedule or plan is to move from Morgan onto Budd Avenue, Avalon Drive, King Ridge Drive and then Luray Drive [hopefully and barring any incident, all planing of these streets shall be completed by late Monday (6/26/17) or early Tuesday (6/27/17)].

Pavement restoration, weather permitting, will take place immediately after milled streets have been properly cleaned and prepped for asphalt. Morgan Avenue should be completed before BalloonFest.

Millings, paving