City of Ashland Paving Project

 Most Recent Updates

paving project

Updates on the Paving Project

In November 2016, the citizens of Ashland voted on and passed an income tax increase of .25 percent to generate additional funding to repave streets in the city. Updates regarding that project will be posted here as they become available.

Please note that the plans are contingent upon the weather and other factors. The contractor for the project is committed to doing a great job for the city and will make every effort to complete the job as efficiently as possible. 

To find out more about how weather conditions affect asphalt, check out this info from the Federal Highway Administration::
Federal Highway Administration Guidelines

In addition to the City of Ashland paving project, some of the main routes through Ashland are maintained by the Ohio Department of Transportation. Click on the following link to see the ODOT plan for Statewide Transportation Improvement Program for Ashland from 2018 to 2021.
ODOT Planned Road Projects 2018-2021

Thank you for your patience as the crews work on the paving. The inconveniences will soon result in a more pleasant ride around the city for all of us!


 


 

Thank you for your assistance in observing the "No Parking" signs that are being posted before the work starts. 

Pavement restoration, weather permitting, will take place immediately after milled streets have been properly cleaned and prepped for asphalt.

 

What's Happening

Sept. 18, 2017 -  Beginning Tuesday, the crews plan to begin paving on Jacobson and Virginia Avenue. Following that area, the crews plan to move on to Cleveland Avenue and Olde Post Road for cleaning and paving.

Sept 11, 2017 - Listed below is the proposed schedule for next week, subject to change and weather dependent as always:

Monday - Paving Clark and Hale
Tuesday - No Work
Wednesday - Final cleanup of Virginia and Jacobson
Thursday - Pavement planing on Cleveland and Olde Post area
Friday - Complete planing in Olde Post area and possibly start South Countryside.

 

 Morgan Avenue 

 

The paving of Morgan Avenue and other area streets during the summer of 2017.

 

 

Past Updates

August 28, 2017 - Phase 3, which includes the following streets,  is scheduled to start later this week!
Note: Franklin and Myers will be included in a future phase.  The Contractor removed them from Phase 2 to ensure that the other scheduled streets were completed before school began.

Phase 3 Update:

Hale Avenue
Lee Avenue
Clark Avenue (East 8th to East 9th)
East 8th Street (Clark to Cleveland)
Virginia Avenue
Jacobson Avenue
(Posted 8/28/2017)
August 23, 2017 - Broad Street should be finished today and then the crews plan to move over to pave Scott, Union, Walnut, Eastern, and Liberty.  As always, the locations are subject to change and dependent on weather. 
August 18, 2017 - Today, Broad Street will be scratch-coated, which is a preliminary coat. The final paving on Broad will follow a little later. 
August 16, 2017 - The Phase 2 streets have all been milled. Resurfacing continues on Baney and the other streets will soon follow. 

August 2, 2017 - There have been some changes on the list of streets for Phase 2. Paving will begin on the following streets beginning Monday, August 7, weather permitting:

Phase 2 Update:

Scott
Broad

Franklin
Baney
East Liberty
Eastern - remainder
West Walnut
Union
(Posted 8/2/2017)

July 30, 2017 - The paving project will resume with Phase 2 during the first week of August. The streets scheduled for resurfacing are listed.

July 25, 2017 -  West Walnut Street will be paved using funding from CDBG (Community Development Block Grant). The bid for West Walnut, between Claremont Avenue and Center Street, has now been awarded. The schedule has not yet been finalized, but the work is planned for this summer or early fall. 

 

 

Millings, paving

 

 

Second Phase:

Arch St
Baney Rd
Broad St
Elmarna Ave
Franklin Ave
Myers Ave
Monroe St
Scott St

(added 7/20/17)

July 14, 2017 - With the improved weather today, the crews plan to finish Eastern Ave and Luray Drive today.

July 11, 2017 - Eastern Ave is scheduled for paving today and then the crews will start on Luray, as there is little chance of rain. 

July 7, 2017 - Work will commence on Eastern Ave today, weather permitting.

July 6, 2017 - Avalon is almost finished while the paving continues on King Ridge Drive. Eastern Ave is scheduled for tomorrow, weather permitting. 

July 5, 2017 - Paving resumes today on King Ridge Drive and Avalon. 

June 30, 2017 - Sarver Paving is performing only cleanup work today and will resume paving next Wednesday when they will finish King Ridge Drive and potentially start on Avalon.  

June 29, 2017 - Budd Avenue and King Ridge Avenue are being paved today, weather permitting.

June 28, 2017 - Morgan Avenue is being paved today. Check back for updated information which will be posted as it is received. 

June 27, 2017 - Eastern Ave, starting at East Main and to Hillcrest has been added to the list for the first phase of the street paving.

First Phase:

Morgan Avenue
Budd Avenue
Avalon Drive
King Ridge Drive
Luray Drive
Eastern Ave
(added 6/27)

June 21, 2017Sarver will begin posting streets for "no parking" Wednesday (6/21/17), then milling (or pavement planing) is to start Friday (6/23/17) around 10:00am on Morgan Avenue. The current schedule or plan is to move from Morgan onto Budd Avenue, Avalon Drive, King Ridge Drive and then Luray Drive [hopefully and barring any incident, all planing of these streets shall be completed by late Monday (6/26/17) or early Tuesday (6/27/17).

Morgan Avenue should be completed before BalloonFest.